Further development of yielding elements and connecting elements for shotcrete

Wulf Schubert, Stefan Brunnegger, Robert Staudacher, Julian Wenger

Research output: Contribution to journalArticleResearchpeer-review

Abstract

Yielding elements in combination with shotcrete linings are used in Austria since 1994, replacing the previous method of leaving open gaps. The first system, used at the Galgenbergtunnel, consisted of groups of axially loaded steel pipes with manufactured local weakness. The resistance of those elements showed a pronounced oscillation during shortening. This triggered a first improvement of the elements in the late 1990ies. Those elements were called LSC (Lining Stress Controller) and subsequently successfully used on a significant number of projects around the world. Recently, the yielding elements have been further optimized aiming at easier production and lower costs. Still using steel pipes, those are filled with porous material, increasing the elements' capacity. With sequential excavation, construction joints in the shotcrete lining are necessary. Producing quality joints appears to be difficult without special connecting elements. The so produced connections are thus potential points of weakness, reducing the lining capacity. A prototype of a connecting element was developed, which can be easily produced and installed. Site tests have been successfully conducted at the tunnel Stein in Austria.

Translated title of the contributionFurther development of yielding elements and connecting elements for shotcrete
Original languageGerman
Pages (from-to)575-581
Number of pages7
JournalGeomechanics and Tunnelling
Volume11
Issue number5
DOIs
Publication statusPublished - 1 Oct 2018

Fingerprint

shotcrete
Linings
pipe
steel
Steel pipe
excavation
tunnel
oscillation
Excavation
cost
Porous materials
Tunnels
Controllers
Costs
material
world
test
method
project

Keywords

    ASJC Scopus subject areas

    • Civil and Structural Engineering
    • Geotechnical Engineering and Engineering Geology

    Fields of Expertise

    • Sustainable Systems

    Treatment code (Nähere Zuordnung)

    • Application

    Cite this

    Weiterentwicklung von Stauchelementen und Spritzbetonanschlüssen. / Schubert, Wulf; Brunnegger, Stefan; Staudacher, Robert; Wenger, Julian.

    In: Geomechanics and Tunnelling , Vol. 11, No. 5, 01.10.2018, p. 575-581.

    Research output: Contribution to journalArticleResearchpeer-review

    Schubert, Wulf ; Brunnegger, Stefan ; Staudacher, Robert ; Wenger, Julian. / Weiterentwicklung von Stauchelementen und Spritzbetonanschlüssen. In: Geomechanics and Tunnelling . 2018 ; Vol. 11, No. 5. pp. 575-581.
    @article{fdddc0d27a574728966dda6b739164dc,
    title = "Weiterentwicklung von Stauchelementen und Spritzbetonanschl{\"u}ssen",
    abstract = "Yielding elements in combination with shotcrete linings are used in Austria since 1994, replacing the previous method of leaving open gaps. The first system, used at the Galgenbergtunnel, consisted of groups of axially loaded steel pipes with manufactured local weakness. The resistance of those elements showed a pronounced oscillation during shortening. This triggered a first improvement of the elements in the late 1990ies. Those elements were called LSC (Lining Stress Controller) and subsequently successfully used on a significant number of projects around the world. Recently, the yielding elements have been further optimized aiming at easier production and lower costs. Still using steel pipes, those are filled with porous material, increasing the elements' capacity. With sequential excavation, construction joints in the shotcrete lining are necessary. Producing quality joints appears to be difficult without special connecting elements. The so produced connections are thus potential points of weakness, reducing the lining capacity. A prototype of a connecting element was developed, which can be easily produced and installed. Site tests have been successfully conducted at the tunnel Stein in Austria.",
    keywords = "connecting elements, Conventional tunnelling, shotcrete lining, Support, yielding elements",
    author = "Wulf Schubert and Stefan Brunnegger and Robert Staudacher and Julian Wenger",
    year = "2018",
    month = "10",
    day = "1",
    doi = "10.1002/geot.201800038",
    language = "deutsch",
    volume = "11",
    pages = "575--581",
    journal = "Geomechanics and Tunnelling",
    issn = "1865-7362",
    publisher = "Ernst & Sohn",
    number = "5",

    }

    TY - JOUR

    T1 - Weiterentwicklung von Stauchelementen und Spritzbetonanschlüssen

    AU - Schubert, Wulf

    AU - Brunnegger, Stefan

    AU - Staudacher, Robert

    AU - Wenger, Julian

    PY - 2018/10/1

    Y1 - 2018/10/1

    N2 - Yielding elements in combination with shotcrete linings are used in Austria since 1994, replacing the previous method of leaving open gaps. The first system, used at the Galgenbergtunnel, consisted of groups of axially loaded steel pipes with manufactured local weakness. The resistance of those elements showed a pronounced oscillation during shortening. This triggered a first improvement of the elements in the late 1990ies. Those elements were called LSC (Lining Stress Controller) and subsequently successfully used on a significant number of projects around the world. Recently, the yielding elements have been further optimized aiming at easier production and lower costs. Still using steel pipes, those are filled with porous material, increasing the elements' capacity. With sequential excavation, construction joints in the shotcrete lining are necessary. Producing quality joints appears to be difficult without special connecting elements. The so produced connections are thus potential points of weakness, reducing the lining capacity. A prototype of a connecting element was developed, which can be easily produced and installed. Site tests have been successfully conducted at the tunnel Stein in Austria.

    AB - Yielding elements in combination with shotcrete linings are used in Austria since 1994, replacing the previous method of leaving open gaps. The first system, used at the Galgenbergtunnel, consisted of groups of axially loaded steel pipes with manufactured local weakness. The resistance of those elements showed a pronounced oscillation during shortening. This triggered a first improvement of the elements in the late 1990ies. Those elements were called LSC (Lining Stress Controller) and subsequently successfully used on a significant number of projects around the world. Recently, the yielding elements have been further optimized aiming at easier production and lower costs. Still using steel pipes, those are filled with porous material, increasing the elements' capacity. With sequential excavation, construction joints in the shotcrete lining are necessary. Producing quality joints appears to be difficult without special connecting elements. The so produced connections are thus potential points of weakness, reducing the lining capacity. A prototype of a connecting element was developed, which can be easily produced and installed. Site tests have been successfully conducted at the tunnel Stein in Austria.

    KW - connecting elements

    KW - Conventional tunnelling

    KW - shotcrete lining

    KW - Support

    KW - yielding elements

    UR - http://www.scopus.com/inward/record.url?scp=85054185312&partnerID=8YFLogxK

    U2 - 10.1002/geot.201800038

    DO - 10.1002/geot.201800038

    M3 - Artikel

    VL - 11

    SP - 575

    EP - 581

    JO - Geomechanics and Tunnelling

    JF - Geomechanics and Tunnelling

    SN - 1865-7362

    IS - 5

    ER -