Abstract

Correlations between calculation parameters directly influence the results of probabilistic calculations and their interpretation. In Monte Carlo simulations carried out to systematically integrate uncertainties into the calculation process, input parameter correlations are reflected by correlation coefficients and predominantly influence the chance/risk ratio and ranges of results. Correlations are usually determined indirectly by analyzing existing data series gathered from measurements, surveys, experiments etc. and investigated with respect to their linear relationship. Another option is to directly determine correlation coefficients based on expert surveys. In 2015-16, Kummer and Hofstadler conducted a survey at Graz University of Technology in which experts provided estimates of the coefficients corresponding to the correlations between certain parameters. These considerations concentrated on the labor intensity of reinforced concrete works expressed by the total labor consumption rate, which indicates the amount of labor required for reinforced concrete works per cubic meter of concrete. The total labor consumption rate of reinforced concrete works must consider all activities carried out within the system, such as shuttering, reinforcing and concreting. This paper presents and interprets survey results shown in violin plots, and M-estimators are derived to deliver sound recommendations for considering correlations when determining the total labor consumption rate of reinforced concrete works. An example demonstrates the influence of input parameter correlations on calculating the total labor consumption rate of reinforced concrete works.

Spracheenglisch
TitelISEC 2017 - 9th International Structural Engineering and Construction Conference: Resilient Structures and Sustainable Construction
Herausgeber (Verlag)ISEC Press
ISBN (elektronisch)9780996043748
StatusVeröffentlicht - 2017
Veranstaltung9th International Structural Engineering and Construction Conference: Resilient Structures and Sustainable Construction, ISEC 2017 - Valencia, Spanien
Dauer: 24 Jul 201729 Jul 2017

Konferenz

Konferenz9th International Structural Engineering and Construction Conference: Resilient Structures and Sustainable Construction, ISEC 2017
LandSpanien
OrtValencia
Zeitraum24/07/1729/07/17

Fingerprint

Reinforced concrete
Personnel
Acoustic waves
Concretes
Experiments

Schlagwörter

    ASJC Scopus subject areas

    • !!Civil and Structural Engineering
    • !!Building and Construction

    Dies zitieren

    Kummer, M., & Hofstadler, C. (2017). Probabilistic calculation of total labor consumption rate of reinforced concrete works -with and without correlations. in ISEC 2017 - 9th International Structural Engineering and Construction Conference: Resilient Structures and Sustainable Construction ISEC Press.

    Probabilistic calculation of total labor consumption rate of reinforced concrete works -with and without correlations. / Kummer, Markus; Hofstadler, Christian.

    ISEC 2017 - 9th International Structural Engineering and Construction Conference: Resilient Structures and Sustainable Construction. ISEC Press, 2017.

    Publikation: Beitrag in Buch/Bericht/KonferenzbandBeitrag in einem KonferenzbandForschungBegutachtung

    Kummer, M & Hofstadler, C 2017, Probabilistic calculation of total labor consumption rate of reinforced concrete works -with and without correlations. in ISEC 2017 - 9th International Structural Engineering and Construction Conference: Resilient Structures and Sustainable Construction. ISEC Press, Valencia, Spanien, 24/07/17.
    Kummer M, Hofstadler C. Probabilistic calculation of total labor consumption rate of reinforced concrete works -with and without correlations. in ISEC 2017 - 9th International Structural Engineering and Construction Conference: Resilient Structures and Sustainable Construction. ISEC Press. 2017
    Kummer, Markus ; Hofstadler, Christian. / Probabilistic calculation of total labor consumption rate of reinforced concrete works -with and without correlations. ISEC 2017 - 9th International Structural Engineering and Construction Conference: Resilient Structures and Sustainable Construction. ISEC Press, 2017.
    @inproceedings{feb4f2fe9e204881a636cfc6f6107f08,
    title = "Probabilistic calculation of total labor consumption rate of reinforced concrete works -with and without correlations",
    abstract = "Correlations between calculation parameters directly influence the results of probabilistic calculations and their interpretation. In Monte Carlo simulations carried out to systematically integrate uncertainties into the calculation process, input parameter correlations are reflected by correlation coefficients and predominantly influence the chance/risk ratio and ranges of results. Correlations are usually determined indirectly by analyzing existing data series gathered from measurements, surveys, experiments etc. and investigated with respect to their linear relationship. Another option is to directly determine correlation coefficients based on expert surveys. In 2015-16, Kummer and Hofstadler conducted a survey at Graz University of Technology in which experts provided estimates of the coefficients corresponding to the correlations between certain parameters. These considerations concentrated on the labor intensity of reinforced concrete works expressed by the total labor consumption rate, which indicates the amount of labor required for reinforced concrete works per cubic meter of concrete. The total labor consumption rate of reinforced concrete works must consider all activities carried out within the system, such as shuttering, reinforcing and concreting. This paper presents and interprets survey results shown in violin plots, and M-estimators are derived to deliver sound recommendations for considering correlations when determining the total labor consumption rate of reinforced concrete works. An example demonstrates the influence of input parameter correlations on calculating the total labor consumption rate of reinforced concrete works.",
    keywords = "Chance/risk ratio, Distribution function, Expert survey, Histogram, Monte Carlo simulation, Violin plot",
    author = "Markus Kummer and Christian Hofstadler",
    year = "2017",
    language = "English",
    booktitle = "ISEC 2017 - 9th International Structural Engineering and Construction Conference: Resilient Structures and Sustainable Construction",
    publisher = "ISEC Press",

    }

    TY - GEN

    T1 - Probabilistic calculation of total labor consumption rate of reinforced concrete works -with and without correlations

    AU - Kummer, Markus

    AU - Hofstadler, Christian

    PY - 2017

    Y1 - 2017

    N2 - Correlations between calculation parameters directly influence the results of probabilistic calculations and their interpretation. In Monte Carlo simulations carried out to systematically integrate uncertainties into the calculation process, input parameter correlations are reflected by correlation coefficients and predominantly influence the chance/risk ratio and ranges of results. Correlations are usually determined indirectly by analyzing existing data series gathered from measurements, surveys, experiments etc. and investigated with respect to their linear relationship. Another option is to directly determine correlation coefficients based on expert surveys. In 2015-16, Kummer and Hofstadler conducted a survey at Graz University of Technology in which experts provided estimates of the coefficients corresponding to the correlations between certain parameters. These considerations concentrated on the labor intensity of reinforced concrete works expressed by the total labor consumption rate, which indicates the amount of labor required for reinforced concrete works per cubic meter of concrete. The total labor consumption rate of reinforced concrete works must consider all activities carried out within the system, such as shuttering, reinforcing and concreting. This paper presents and interprets survey results shown in violin plots, and M-estimators are derived to deliver sound recommendations for considering correlations when determining the total labor consumption rate of reinforced concrete works. An example demonstrates the influence of input parameter correlations on calculating the total labor consumption rate of reinforced concrete works.

    AB - Correlations between calculation parameters directly influence the results of probabilistic calculations and their interpretation. In Monte Carlo simulations carried out to systematically integrate uncertainties into the calculation process, input parameter correlations are reflected by correlation coefficients and predominantly influence the chance/risk ratio and ranges of results. Correlations are usually determined indirectly by analyzing existing data series gathered from measurements, surveys, experiments etc. and investigated with respect to their linear relationship. Another option is to directly determine correlation coefficients based on expert surveys. In 2015-16, Kummer and Hofstadler conducted a survey at Graz University of Technology in which experts provided estimates of the coefficients corresponding to the correlations between certain parameters. These considerations concentrated on the labor intensity of reinforced concrete works expressed by the total labor consumption rate, which indicates the amount of labor required for reinforced concrete works per cubic meter of concrete. The total labor consumption rate of reinforced concrete works must consider all activities carried out within the system, such as shuttering, reinforcing and concreting. This paper presents and interprets survey results shown in violin plots, and M-estimators are derived to deliver sound recommendations for considering correlations when determining the total labor consumption rate of reinforced concrete works. An example demonstrates the influence of input parameter correlations on calculating the total labor consumption rate of reinforced concrete works.

    KW - Chance/risk ratio

    KW - Distribution function

    KW - Expert survey

    KW - Histogram

    KW - Monte Carlo simulation

    KW - Violin plot

    UR - http://www.scopus.com/inward/record.url?scp=85027880081&partnerID=8YFLogxK

    M3 - Conference contribution

    BT - ISEC 2017 - 9th International Structural Engineering and Construction Conference: Resilient Structures and Sustainable Construction

    PB - ISEC Press

    ER -